Anzob Tunnel

Anzob Tunnel
Anzob Tunnel South Entrance, 2015
Operation
Opened1 March 2005; 19 years ago (2005-03-01)
Technical
Length5,040 m (3.13 mi)
Highest elevation2,720 m (8,920 ft)
Lowest elevation2,670 m (8,760 ft)

The Anzob Tunnel, Istiqlol tunnel or Ushtur Tunnel is a 5,040 m long tunnel located 80 km (50 mi) northwest of Tajikistan's capital Dushanbe, at an elevation of 2,720 m (8,920 ft). The tunnel is part of the M34 highway and connects the Tajik capital to the country's second largest city, Khujand. The tunnel was opened in 2006 despite being only partially finished.[citation needed] In 2014 Iran's government signed an agreement to finish the tunnel and the tunnel was reopened in late 2015. The tunnel saves drivers at least 4 hours when traveling between Dushanbe and Khujand and allows travelers to avoid having to pass through Uzbekistan.

Strategic importance

Its construction put an end to Uzbekistan's ability to halt traffic between Tajikistan's two largest cities (the two countries have suffered from long-term diplomatic disputes). It marked the beginning of other major co-operative projects such as the Sangtuda-2 power plant.

The tunnel is also said to be part of a planned road which would run from Iran through Herat in western Afghanistan and Mazar-i-Sharif and Sherkhan Bandar in northern Afghanistan to Tajikistan and from there up to China. The route has been named the new Silk Road.[citation needed]

It is also a transit route between Dushanbe and Uzbekistan's capital Tashkent. Prior to construction of the tunnel, especially during winter, the threat of year-round avalanches led to periodic disruptions of commerce.

Construction timeline

The tunnel in 2011, five years after its opening but still without pavement, ventilation or lighting.

The tunnel was officially opened in March 2006; it was built by the Iranian Sabir Co.[1] Due to the significance of the tunnel, limited traffic flow was permitted via signing a waiver form noting potential hazards such as flooding and smog from construction equipment operating inside the tunnel prior to the final construction phase which may have included installation of ventilation and drainage infrastructure.[2]

Workers pose following the tunnel's repairs and reopening

As of May 2014, the tunnel was still unfinished and the Iranian government and Tajik government had signed an agreement to complete the project by late March 2015.[3] The tunnel was closed in June 2015 for repair work and reopened for traffic in September 2015 after leakage problems and concreting the base and lighting the tunnel was completed.[4][5] It was officially inaugurated in August 2017.[6]

References

  1. ^ "Российско-Китайское торгово-экономическое сотрудничество". Crc.mofcom.gov.cn. Archived from the original on 14 January 2014. Retrieved 7 February 2014.
  2. ^ "Anzob tunnel - Lonely Planet travel forum". Lonelyplanet.com. Retrieved 7 February 2014.
  3. ^ "Envoy: Iran to complete Tajikistan's independence tunnel by next year". The Iran Project. 8 May 2014. Retrieved 3 October 2019.
  4. ^ "Istiqlol Tunnel reopened for traffic for all types of vehicles today". Tajikistan News-NA «Asia-Plus». 25 September 2015. Archived from the original on 10 January 2019. Retrieved 13 October 2015.
  5. ^ Iran-made tunnel connects Tajikistan’s north to its south, published on 8 December 2015, Press TV
  6. ^ http://en.iwpco.ir/Lists/News/DispForm.aspx?ID=186. Retrieved 3 October 2019. {{cite web}}: Missing or empty |title= (help)

39°05′16″N 68°41′34″E / 39.0879°N 68.6927°E / 39.0879; 68.6927