Dagenham wind turbines

51°31′19″N 0°9′4″E / 51.52194°N 0.15111°E / 51.52194; 0.15111Commission date2004Owner(s)Ford Motor CompanyPower generation Units operational3 Enercon turbinesNameplate capacity5.9 MW
[edit on Wikidata]

The Dagenham wind turbines are two 85-metre (279 ft) high Enercon E-66 and one E-82[1] wind turbines located on the Dagenham estate of the Ford Motor Company in East London, England.[2] The first two turbines were completed in April 2004 and the third was installed in 2011.[3] They are landmarks of the skyline and the first wind farm to be built in London.[4]

Planning and building

One turbine is located in the London Borough of Barking and Dagenham, (Turbine 1)[5] the second in the Hornchurch Marshes area of the London Borough of Havering (Turbine 2).[5] Planning consent was received from both boroughs.[6] The Mayor of London gave approval for the project in August 2003.[7]

The turbines were constructed by the green energy company Ecotricity.[2] Planning consent was also given for a third 65-metre (213 ft) high turbine (Turbine 3)[5] in Havering, with a viewing platform which was not constructed.[6][7] The planned operating date for the third wind turbine was by the first quarter of 2009,[1] and it was eventually installed in 2011.[3]

Specifications

The turbines are located 10 miles (16 km) east of the City of London at OS grid reference TQ492824 and TQ502818. They are 85 metres (279 ft) high to the hub, have a rotor diameter of 70 metres (230 ft) and a combined capacity of 5.9 MW. The total height to the top of the rotors is 120 metres (390 ft).[5]

Location

Map all coordinates using OpenStreetMap

Download coordinates as:

  • KML
  • GPX (all coordinates)
  • GPX (primary coordinates)
  • GPX (secondary coordinates)
Point Coordinates
(links to map & photo sources)
Notes
Turbine 1 51°31′19″N 0°09′04″E / 51.5220°N 0.1510°E / 51.5220; 0.1510 (Turbine 1) 1.8 MW
Turbine 2 51°30′58″N 0°09′53″E / 51.5160°N 0.1648°E / 51.5160; 0.1648 (Turbine 2) 1.8 MW
Turbine 3 51°30′45″N 0°09′56″E / 51.5125°N 0.1656°E / 51.5125; 0.1656 (Turbine 3) 2.3 MW


Gallery

  • Turbine 2
    Turbine 2
  • Turbine 1 and several structures of the Ford plant
    Turbine 1 and several structures of the Ford plant
  • Beam valley and turbine 2
    Beam valley and turbine 2
  • A Ford Mondeo before one of the turbines
    A Ford Mondeo before one of the turbines

References

  1. ^ a b "Third Turbine To Support Ford Plant". 24 April 2008. Retrieved 8 December 2008.
  2. ^ a b "London's first wind park at Ford, Dagenham". Archived from the original on 1 March 2003.
  3. ^ a b "Ford Dagenham's Third Wind Turbine Turns Up More Green Power". 15 August 2011. Archived from the original on 12 May 2012.
  4. ^ "Thames Gateway London Partnership" (PDF). September 2004. Archived from the original (PDF) on 30 September 2007.
  5. ^ a b c d "Wind Turbines, Ford Estate, Dagenham planning application". Greater London Authority. 4 June 2003. Archived from the original on 30 September 2007.
  6. ^ a b "Huge wind turbines win approval". BBC News. 27 August 2003.
  7. ^ a b "The Mayor's planning decisions - meeting date 04 June 2003". Archived from the original on 30 September 2007.
  • flagEngland portal
  • iconWeather portal
  • iconRenewable energy portal
  • v
  • t
  • e
Companies
Onshore wind farms
Active
Proposed
Offshore wind farms
Active
Proposed
Cancelled
Installation vessels
  • MPI Adventure
  • MPI Resolution
  • MPI Discovery
Other
  • icon Wind power portal
  • Category
  • Commons
  • v
  • t
  • e
Companies and
organisations
Current
Former
Power stations
Biomass
Active
Coal
Closed
Gas
Active
Closed
Future
Incinerators/
waste
Active
Closed
  • Shoreditch
Oil
Active
Closed
Wind
Active
  • Dagenham