Tazama Pipeline

Crude oil pipeline
Tazama Pipeline
Tazama Oil Depot
Tazama Oil Depot
Location
CountryTanzania and Zambia
General directionEast to West
FromDar-es-Salaam, Tanzania
ToNdola, Zambia
General information
TypeCrude oil
PartnersGovernment of Tanzania and Government of Zambia
OperatorTazama Pipeline Limited
Commissioned1968; 56 years ago (1968)
Technical information
Length1,710 km (1,060 mi)
Maximum discharge1,100,000 tonnes (1,212,542 tons) annually
No. of pumping stations7

The Tazama Pipeline, also Tanzania–Zambia Crude Oil Pipeline, is a 1,710 kilometres (1,063 mi) long crude oil pipeline from the port of Dar-es-Salaam, Tanzania, to the Indeni Petroleum Refinery in Ndola, Zambia.[1]

Location

The Tazama pipeline extends from the Indian Ocean port of Dar es Salaam, in Tanzania to the industrial city of Ndola, Zambia, in the Copperbelt Province, close to the border with the Democratic Republic of the Congo. The pipeline travels approximately 1060 miles (1,710 kilometers).[2] For 954 kilometres (593 mi) the pipeline has a diameter of 8 inches (200 mm), and for the remaining 798 kilometres (496 mi), the pipeline diameter is 12 inches (300 mm).[2] According to the map at the pipeline website, the pipeline passes through or near the following cities and towns: Dar es Salaam, Morogoro, Epass, Iringa, Mbeya, Chinsali, Mpika, Kalonje and Ndola.[2]

Overview

The Tazama Crude Oil Pipeline was constructed to transport crude oil from the port of Dar-es-Salaam into landlocked Zambia, at an affordable, sustainable economic cost. When installed in 1968, the pipeline had a carrying capacity of 1,100,000 tonnes (1,212,542 tons) annually.[2] By 2002, carrying capacity had deteriorated to 600,000 tonnes (661,387 tons) annually.[1]

Associated infrastructure owned by Tazama in Tanzania, includes the tank farm in Dar es Salaam consisting of six storage tanks onshore, which comprise three tanks of 36,000 cubic meters (36,000,000 L) capacity combined and three tanks of combined capacity of 41,000 cubic meters (41,000,000 L). There are seven pump stations in total between Dar-es-Salaam and Ndola; five stations in Tanzania and two in Zambia.[1]

Ownership

The pipeline is owned and operated by a company called Tazama Pipelines Limited, with headquarters in Ndola Zambia and an office in Dar es Salaam, Tanzania. TAZAMA stands for Tanzania Zambia Mafuta. "Mafuta" means "Oil" in Kiswahili.[2] The table below illustrates the shareholding in the shares of stock of Tazama Pipelines Limited.[1][2]

Shareholding in the stock of Tazama Pipelines Limited
Rank Name of owner Percentage ownership
1 Government of Zambia
66.70
2 Government of Tanzania
33.30

Operation

Due to age and lack of regular maintenance, the Tazama pipeline suffers corrosion and develops leaks from time to time. Repair of those leaks is necessary to avoid environmental degradation.[3][4]

Due to inability by Tazama Pipeline and Indeni Petroleum Refinery to supply all the refined petroleum products that Zambia requires, in the desired quantities, the government of Zambia and that of Tanzania, are contemplating building a 1,349 kilometres (838 mi) refined petroleum products pipeline at an estimated cost of US$1.5 billion. No timeframe has been given.[5]

References

  1. ^ a b c d Zambia Privatisation Agency (6 August 2002). "Description of the Tazama Pipeline". Lusaka: Zambia Privatisation Agency. Archived from the original (Archived from the original on 24 September 2006) on 24 September 2006. Retrieved 21 May 2020.
  2. ^ a b c d e f Tazama Pipeline Limited (21 May 2020). "Tazama Pipeline Limited: Who We Are". Ndola: Tazama Pipeline Limited. Retrieved 21 May 2020.
  3. ^ AfDB (20 May 2020). "Zambia: Tazama Pipeline Rehabilitation Project". Abidjan, Ivory Coast: African Development Bank (AfDB). Retrieved 21 May 2020.
  4. ^ Energy Unit, Africa Region (28 June 2001). "Zambia Petroleum Rehabilitation Project: Implementation Completion Report" (PDF). Washington, DC: World Bank. Retrieved 21 May 2020.
  5. ^ George Obulutsa (28 May 2019). Jane Merriman (ed.). "Tanzania, Zambia plan $1.5 billion oil products pipeline: Tanzania minister". Reuters. Retrieved 21 May 2020.

External links

  • Official Website
  • Zambia Set for a Fuel Pipeline Upgrade As of 25 September 2023.


13°02′26″S 28°40′48″E / 13.04056°S 28.68000°E / -13.04056; 28.68000